Testing and commissioning is all complete and RBSS has formerly handed over the Jindong Treeton Farm project to the owners.
The new 60kWh Redflow battery energy storage system takes the property completely off-grid – providing 3-phase power to the farm’s two homes, one hayshed and workshop.
System specifications:
- 6 x 10kWh Redflow ZBM2 Battery Storage
- 3 x 10kVA Victron Quattro Inverter/Chargers
- 4 x Victron MPPT Controllers
- 24.5kW Rooftop PV Array
- 5kW Wind-turbine