TIEC has laid down the concrete slab at Bonza Station ready for the purpose-built substation to go on.

The substation will eventually house:

  • 3 x 10kWh ZBM2 batteries providing 30kW/h storage
  • Victron MPPT solar charges
  • 1 x 15kVA Victron Quattro Inverter / Charger
  • Distribution electrical switchboard